TASK STATUS FOR THE 2004-05 UPWP
Continuing Tasks in both the 2003-04
and 2004-05 UPWPs
Task Lead
Agency 04-05 Comments
1.51 Committee Activities CDTC
1.52 Financial Administration NYSDOT/CDTC
1.61 Certification Review CDTC formal review in FFY04
1.65 UPWP Development and Monitoring CDTC develop 2005-06 UPWP
1.66 DBE/Title VI Program Update CDTC Envir.
Justice work continues
1.68 Statewide MPO
Administration CDTC continue consultant
support
2.16 Microcomputer Model Refinement CDTC continue development of
new model
2.30 Routine Highway Condition Inventory CDTC non-federal-aid system in 2004
2.31 Traffic Volume Report CDTC web-based, continual
updates
2.25 Collection of Transp Planning Support Data CDTC continued
heavy use of interns
2.28 Census Transp. Planning Package CDTC further Census data
rollout in 2004
2.29 Geog.Info System for Transp. CDTC coordinate
with new traffic model
3.77 New Visions CDTC New Visions 2030,
Quality Region
3.05 Infrastructure Renewal Planning CDTC resource review for New
Visions 2030
3.06 Goods Movement Planning CDTC continued task force
support
3.10 I-87 Corridor CDTC phase 2 in 04-05;
NYSDOT lead
3.86 Continuous Aviation System Planning CDRPC
3.01 Management Systems CDTC development of Safety
Mgt. System;
update of CMS data, process
3.02 Air Quality Planning CDTC conformity continues
3.11 REVEST CDTC folded into
4.07
4.17 Arterial Management Planning CDTC revise, update
standards
4.62 Transit Operations Planning CDTA Major route redesign
efforts
4.67 Bicycle and Pedestrian Planning CDTC Plan refinement; trail
map, logo
4.97 TIP Development, Monitoring and Update CDTC develop
2003-08 TIP
5.51 General Technical Services CDTC continued local support
5.61 Project Development Support CDTC
/ NYSDOT TIP Implementation
5.67 Linkage Project Oversight CDTC continuing, larger
budget
5.52 General Community Services CDTC
5.57 Commuter Support Services CDTC continue electronic
operation
5.60 Public Transit Planning Support CDTC
/ CDTA linkage to New
Visions
5.62 Corridor Management Initiative Municipalities
/ CDTC / NYSDOT covers costs of NY5 BRT
design
5.63 Demand Management CDTA/
NYSDOT / CDTC pilot CMAQ program
5.86 Clean Communities Program CDTC continuing without DOE
funding
TASK STATUS FOR THE 2004-05 UPWP
Carryover tasks from 2003-04
and New Tasks in the 2004-05 UPWP
Task Lead
Agency 04-05 Comments
1.67 Prospectus CDTC to reflect NYSDOT transformation
deferred to 04-05
3.12 Transit Service Design Guidelines CDTC/CDTA deferred to 04-05, expanded
4.18 ITS Architecture and Integration CDTC/NYSDOT complete in 03-04
4.67 Greenways Study, Albany County CDTC complete in 03-04
5.62 NY 5 Corridor Support CDTC continuing
5.68 Pinebush Update CDTC complete in 03-04
5.74 Glenville Town Center Master Plan Glenville complete in 03-04
5.77 Hoosick Street Integration Troy complete in 03-04
5.79 McKownville Corridor Guilderland complete in 03-04
5.80 Malta DISTRICT Study
5.81 Lansingburgh Study Troy complete in 03-04
5.82 Freeman's Bridge / Dutch Meadows Plan Glenville complete
in 03-04
5.84 NY 5 Corridor Tools CDTC carryover
5.85 Integrated Transp. / Community Design CDTC complete in 04-05
5.87 Albany Mansion Neighborhood Parking CDTC complete in 03-04
5.88 Ballston/Malta Route 67 study CDTC carryover, complete in
04-05
5.89 Charlton Main St. CDTC complete in 03-04
5.90 East Greenbush 9 &20 CDTC complete in 03-04
5.91 East Greenbush NY 151 CDTC complete in 03-04
5.92 Guilderland: Ft. Hunter/Carman CDTC complete in 03-04
5.93
5.94
5.95
5.96
5.97 Thruway Capacity Study Thruway
Authority carryover,
complete in 04-05
5.98 North Greenbush I-90 Land Use Study North
Greenbush carryover, TIP
funded, compl in 04-05
5.99 Balltown Rd. Capacity & Land Use Study CDTC rolled back into TIP project
5.01 Arbor Hill Gateway Planning CDTC carryover, not yet
underway
5.03
5.04 East Greenbush Route 4 CDTC carryover, not yet
underway
5.05 Greenway Study, Rensselaer County CDTC carryover, underway
5.06 Halfmoon Center Roadways CDTC carryover, underway
5.07
5.08 Patroon Greenway Trail Study CDTC carryover, underway