Table 4A

Capital District Transportation Committee
Transportation Improvement Program

Fiscal Constraint By Fund Source By Program Year (2019-24)
All funds are in matched millions of dollars.
Updated 11-23-2022, 12:01 PM

5th Year: 2023-24 Total: 2019-24
Fund Source Budget Estimate Program
Capacity
Budget Estimate Program
Capacity
National Hwy Performance Program 44.746 -8.635 243.075 15.928
STP Flexible 7.868 3.823 46.532 4.063
STP Urban 5.925 -15.156 56.359 -2.756
HSIP Highway 2.668 -2.437 21.073 -0.989
STP NFA Bridges 0.350 0.350 2.480 0.022
Total 61.557 -22.055 369.519 16.268
% Under/Over-programmed -- 36% over -- 4.4% under

The 'Budget Estimate' is the amount of authorized federal funds (including match), including carryover funds from the period prior to 2019-20. Amounts available are based upon the historic Capital District shares of amounts allocated to NYSDOT Region 1.

'Program Capacity' is the difference between the amount available and the amount programmed. Negative numbers indicate overprogramming. The fiscal constraint data above is shown only for the years and federal fund sources for which it applies.