Project Description
Mohawk-Hudson Bike Trail This project will construct a class 1 trail that would connect two existing class 1 trails in the City of Schenectady. Federal funding is 50%, with a maximum of $.3045M.
This project will construct a class 1 trail that would connect two existing class 1 trails in the City of Schenectady. Federal funding is 50%, with a maximum of $.3045M.
Federal funding is 50%, with a maximum of $.3045M.
Funding by Federal Fiscal Year (10/1 to 9/30)
Fund Source
1998-99
1999-00
2000-01
2001-02
2002-03
2003-04
Post '04
Funding Totals by Phase
Phase
Five-Year Funding
Six-Year Funding
Construction
Total
Other Information
TIP Number: S156 Letting Date: FFY '00
Letting Date: FFY '00
PIN: NA Func. Class: NA
Func. Class: NA
Project Type: Bike/Ped Length: .33 cl-mi
Length: .33 cl-mi
Jurisdiction: County Plan Ref.: NV
Plan Ref.: NV
Location: Schenectady No EIS Required
No EIS Required
Implementer: County Air Quality: Exempt
Air Quality: Exempt