Project Description
Ballston Avenue, from Union Street to Hamilton Street: Safety Improvements Reconstruction with a left turn lane, curb realignment, traffic signal replacement, sidewalks and streetscaping.
Reconstruction with a left turn lane, curb realignment, traffic signal replacement, sidewalks and streetscaping.
Funding by Federal Fiscal Year (10/1 to 9/30)
Fund Source
2005-07
2007-08
2008-09
2009-10
2010-11
2011-12
Post '12
Funding Totals by Phase
Phase
Five-Year Funding
Seven-Year Funding
Engineering
Construction
Total
Other Information
TIP Number: SA201
Func. Class: UPA
PIN: 1756.60
Length: NA
Project Type: Safety
Plan Ref.: ITS
Jurisdiction: City
No EIS Required
Location: Saratoga Springs
Air Quality: Exempt
Implementer: City