Watervliet Shaker Road, from Karner Road
to Albany Shaker Road: Corridor
Improvements, Phase 2
Phase 2 is from Sand Creek Road to
Albany Shaker Road
Private financing is per GEIS mitigation
process. None was available at the time
of construction, so STP-Flex made up the
difference. Later mitigation fees will
be held in escrow to offset costs of
other projects.
2003-04 work includes enviornmental
mitigation for project A275 from the
2001-06 TIP.
Phase 1 was project A294 from the
1997-02 TIP. Phase 3 is A453
.
|