Project Description
NY 5 Bus Rapid Transit (BRT) Vehicles Twelve vehicles are to be purchased under this project. Due to an icrease in the unit costs of buses, this porject is now unfunded by $1.250M.
Twelve vehicles are to be purchased under this project. Due to an icrease in the unit costs of buses, this porject is now unfunded by $1.250M.
Due to an icrease in the unit costs of buses, this porject is now unfunded by $1.250M.
Funding by Federal Fiscal Year (10/1 to 9/30)
Fund Source
2003-05
2005-06
2006-07
2007-08
2008-09
2009-10
Post '10
Funding Totals by Phase
Phase
Five-Year Funding
Seven-Year Funding
Vehicles
Total
Other Information
TIP Number: T69
Letting Date: Multiple
PIN: **
Func. Class: NA
Project Type: CapitalVeh
Length: NA
Jurisdiction: CDTA
Plan Ref.: ADA
Location: Regional
No EIS Required
Implementer: CDTA
Air Quality: Exempt