Project Description
Bicycle and Pedestrian Path Near Lock 8 This project provides a bike/ped path connecting Charles Street with Maalwyck Park and the New York State Fishing Access Site at Lock 8. Federal funding is 80%, with a maximum of $0.248M, even though the current estimated cost is lower.
This project provides a bike/ped path connecting Charles Street with Maalwyck Park and the New York State Fishing Access Site at Lock 8. Federal funding is 80%, with a maximum of $0.248M, even though the current estimated cost is lower.
Federal funding is 80%, with a maximum of $0.248M, even though the current estimated cost is lower.
Funding by Federal Fiscal Year (10/1 to 9/30)
Fund Source
2003-05
2005-06
2006-07
2007-08
2008-09
2009-10
Post '10
Funding Totals by Phase
Phase
Five-Year Funding
Seven-Year Funding
Construction
Total
Other Information
TIP Number: S143
Letting Date: FFY '06
PIN: 1754.66
Func. Class: NA
Project Type: Bike/Ped
Length: .75 miles
Jurisdiction: Town
Plan Ref.: Canal
Location: Glenville
No EIS Required
Implementer: Town
Air Quality: Exempt