Transit-Oriented Obligations 2009-10 FFY
Project TIP # NYSDOT Pin 100% Amount Grant Number Date of Obligation
           
Preventative Maintnenance T57    $      14,034,750 NY-90-X637 August-10
Bus Shelters T11 1821.18  $           400,000 NY-90-X637 August-10
Rehab/Renov Signage T11 1821.18  $           100,000 NY-90-X637 August-10
       $      14,534,750    
           
Buy Replacement 40Ft Bus T17 1820.48  $        3,520,000 NY-77-0002-01 March-10
           
           
Capital Cost of Third Party Contracting T77 CDTC12  $        3,745,238 NY-90-X631-01 March-10