Transit-Oriented Obligations 2008-09 FFY |
|
|
|
|
|
|
Project |
TIP # |
NYSDOT Pin |
100% Amount |
Grant Number |
Date of Obligation |
|
|
|
|
|
|
Preventative Maintenance |
T57 |
|
$
8,672,800 |
NY-90-X604 |
November-08 |
Shelter Program |
T11 |
1821.18 |
$
400,000 |
NY-90-X604 |
November-08 |
Rehab/Rebuild 40Ft Bus |
|
|
$
900,000 |
NY-90-X604 |
November-08 |
Buy Replacement 40Ft Bus |
T17 |
1820.48 |
$
2,800,000 |
NY-90-X604 |
November-08 |
|
|
|
$ 12,772,800 |
|
|
|
|
|
|
|
|
Preventative Maintnenance |
T57 |
|
$
13,342,650 |
NY-90-X616 |
September-09 |
Bus Shelters |
T11 |
1821.18 |
$
400,000 |
NY-90-X616 |
September-09 |
Rehab/Renov Signage |
T11 |
1821.18 |
$
100,000 |
NY-90-X616 |
September-09 |
|
|
|
$ 13,842,650 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Capital Cost of Third
Party Contracting |
T77 |
CDTC12 |
$
1,698,000 |
NY-90-X600-01 |
December-08 |
|
|
|
|
|
|
|
|
|
|
|
|
Buy Replacement 40Ft Bus |
T17 |
1820.48 |
$
4,000,000 |
NY-95-X012-01 |
May-09 |
Eng/Design
Controls/Signals |
A462,A463 |
IT0916,IT0917 |
$
111,000 |
NY-95-X012-01 |
May-09 |
|
|
|
$
4,111,000 |
|
|
|
|
|
|
|
|
Buy Replacement 40Ft Bus |
T17 |
1820.48 |
$
1,431,240 |
NY-96-X001-01 |
July-09 |
Buy Replacement 40Ft Bus |
T17 |
1820.48 |
$
13,176,000 |
NY-96-X001-01 |
July-09 |
Buy Replacement <30Ft
Bus Shuttles |
T59 |
1820.57 |
$
721,796 |
NY-96-X001-01 |
July-09 |
Buy Replacement <30Ft
Bus Paratransit |
T6B |
1820.37 |
$
408,064 |
NY-96-X001-01 |
July-09 |
|
|
|
$ 15,737,100 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|