appendix H – CDTC’s Merit Evaluation Procedure
Benefit to cost ratios are calculated by CDTC staff whenever
possible. They are shown in the box in
the upper right-hand corner of the project fact sheet. Consistent units of thousands of current
dollars per year are used throughout.
Instances where a benefit/cost ratio calculation is inappropriate or
unable to be calculated are handled by further elaboration of the
"non-quantifiable" or "qualitative" project benefits. Bicycle and pedestrian projects are handled
differently, as explained below.
Five
measures of project benefit are calculated, including safety, travel time,
energy/user, and "other" benefits.
Life cycle cost savings are applied primarily to infrastructure
improvements. Life cycle cost savings
are calculated by using the CDTC STEP Model to estimate the system traffic disbenefits of letting a bridge or pavement section
deteriorate to the point of abandonment.
Safety benefits are measured in the dollar value of the projected
reduction in accidents per year. They
are the product of the average annual accidents, the expected percent reduction
in accidents as a result of the improvement and a monetary equivalence factor
from a standardized table developed by NYSDOT.
Using ArcView GIS and linked data from NYSDOT,
accident data were obtained for each of the candidate project segments for the four-year
period of 1998 through 2001 for state roads and the three-year period of 1998
through 2000 for non-state roads. For projects proposed on
Accident Reduction Factors
Accidents were identified as intersection or link related, or in the case
of projects proposing to realign curves, curve-related link accidents. Motor vehicle only accidents were
distinguished from motor vehicle/pedestrian or motor vehicle/bicycle
accidents. Improvements had reduction
factors for roads with AADT's greater than 5,000 per lane and those with
less. The majority of accident reduction
factors used in this analysis were obtained from NYSDOT and are found in Table
H-1 on page H-3.
Supplemental accident reduction factors were obtained from other sources
and are found in Table H-1A on page H-7.
Accident
reduction factors were separated into various groups: those that could be
applied project-wide against link accidents, those that could be applied
project-wide against intersection accidents, those to be applied at distinct
locations within the project limits (i.e. curves) and those that could be
applied against bicycle/motor vehicle or pedestrian/motor vehicle accidents
only. Examples of project wide accident
reduction factors include drainage improvements or shoulder widening. Intersection channelization
or realignment of horizontal curves are factors related to intersections or
distinct locations.
Application of
Accident Reduction Factors
Information
regarding planned improvements to be undertaken for each proposed project was
obtained from the Project Justification Packages submitted to CDTC. Project improvements for which an applicable
accident reduction factor was available were then identified and corresponding
average accident reduction factors tallied.
For the vast majority of projects, more than one accident reduction
factor was applicable. In these cases,
the average was applied, consistent with methodology used by NYSDOT to estimate
the potential safety benefits of projects.[1]
The estimated number of accidents reduced annually for each component
(intersections, links, bicycle, and pedestrian accidents) was calculated and a
grand total for the project produced.
Safety benefits were then calculated by multiplying the average annual
accident cost by the number of accidents reduced.
Accident Costs
Average annual accident costs for all facility types were
supplied by NYSDOT[2]. These averages were then aggregated into one
average for all urban facility types and one for rural facility types as shown
in Table H-2 on page H-8.
Costs are not segregated by the type of damage (fatality, injury, or
property damage only).
ACCIDENT Reduction Factors
|
Improvement |
Average
Reduction |
Remarks |
||||||
|
INTERSECTION IMPROVEMENTS |
|
|
||||||
|
Channelization |
37/35 |
Right angle 58%/48%, Rear and overturn
(OT) 30%/53%, Left turn 49% |
||||||
|
Add left turn lane with
physical separation |
26/-- |
Head on/sideswipe (SS) 79%/79% |
||||||
|
Add left turn lane with
painted separation |
45/50 |
Right-angle 63%/62%,
rear-end/OT 39%/54%, left turn 35%/57% |
||||||
|
Add right turn lane with physical
separation |
--/-- |
Limited data |
||||||
|
Add pavement markings to reduce size of intersection |
--/-- |
Limited data |
||||||
|
Other channelization |
24/36 |
Right angle 47%/45% Rear end/OT 33%/76% |
||||||
|
|
|
|
||||||
|
Traffic Signals/Devices |
19/34 |
Right angle 34%/50%, Rear
end/OT 26%/39%, Left turn 18%/26%, Head on/SS 39%/23% |
||||||
|
Other signal improvements |
15/23 |
Right angle 22%/30%, Rear
end/OT 25%/39% |
||||||
|
Install stop ahead signs |
15/15 |
|
||||||
|
4-way stop signs |
73/73 |
|
||||||
|
Install minor leg stop control |
1/1 |
|
||||||
|
Install yield signs |
23/23 |
|
||||||
|
Install new flashing
red/yellow signal |
26/25 |
Right-angle 36%/35% |
||||||
|
Change in operation to
flashing red/yellow signal |
--/-- |
Limited data |
||||||
|
Install new red/yellow/ green
signal |
20/38 |
Right-angle 43%/74%,
rear-end/sideswipe 20%/22% |
||||||
|
Upgrade red/yellow/green
signal. (Includes larger lenses,
better placement of heads, phase adjustment and general signal upgrades) |
19/37 |
Right-angle 37%/47%,
rear-end/OT 26%/41%, left turn 26%/38%, Head on/SS 52%/32% |
||||||
|
Left turn protection (change # of phases) |
36/30 |
Right angle 56%/54%, rear
end/OT 35%/27%, left turn 46%/41% |
||||||
|
Add pedestrian signals |
13/13 |
Detailed engineering analysis
recommended |
||||||
|
Change in signal operation,
from pre-timed to traffic- actuated |
28/39 |
Rear-end/sideswipe 26%/53%,
right angle 32%/41%, Head on/sideswipe 60%/81% |
||||||
|
Channelization & Signals/Devices |
8/41 |
Right angle 30%/66%, rear
end/OT 26%/49% |
||||||
|
Add left-turn lane with signal
(physical) |
19/51 |
Right-angle 55%/68%,
rear-end/OT 28%/50%, left turn 24%/24% |
||||||
|
Add left-turn lane with signal
(painted) |
16/30 |
Right-angle 49%/64% |
||||||
|
Add right-turn lane with
signal |
--/-- |
Limited data |
||||||
|
Add left & right turn lane
with signal |
14/41 |
Right-angle 42%/70, and
rear-end/sideswipe 38%/64% |
||||||
|
Sight distance improvement |
31/31 |
|
||||||
|
Other intersection work |
--/41 |
Right angle /69% |
||||||
|
Prohibit turning movement |
40/40 |
|
||||||
|
Prohibit Parking |
32/32 |
|
||||||
|
|
|
|
||||||
|
Cross-Sectional improvements |
|
|||||||
|
Pavement Widen, No Lanes Added |
59/37 |
Left turn 69%/77% |
||||||
|
Widen travel way from 9 feet |
--/-- |
Limited data |
||||||
|
Widen travel way from 10 feet |
59/37 |
Left turn 69%/77% |
||||||
|
|
|
|
||||||
|
Lanes Added, Without New Median |
31/20 |
Right angle 45%/35%, Rear
end/OT 52%/42%, head-on/sideswipe 44%/38% |
||||||
|
Add additional lanes same
alignment |
31/20 |
Rear end/OT 52%/42%,
head-on/sideswipe 44%/38%, right angle 45%/35%, increased right turn
79%/79% |
||||||
|
Add climbing lane |
--/-- |
Limited data |
||||||
|
Divided Highway, New Flush
Median |
44/24 |
Rear end/OT 41%/44%, Left turn
78%/59%, Head on/sideswipe 57%/60% |
||||||
|
Add flush median |
52/44 |
Left turn 78%/72% |
||||||
|
Add flush median with refuge
for left turns |
44/24 |
Rear-end/OT 40%/44%,
head-on/sideswipe 52%/55%, left-turn 77%/58%, increased right turn 95%/95% |
||||||
|
Widen flush median |
--/-- |
Limited data |
||||||
|
|
|
|
||||||
|
Shoulder Widening or
Improvements |
--/-- |
Limited data |
||||||
|
Shoulder stabilization |
--/-- |
Limited data |
||||||
|
Widening existing shoulder |
17/17 |
For 2-lane roads only |
||||||
|
Add additional lane w/median,
same alignment |
20/20 |
General reconstruction |
||||||
|
|
|
|
||||||
|
Skid Treatment W/Grooving |
22/37 |
Rear end/OT 35%/54%, wet road
54%/64%, Run off the road (ROR) 40%/41%, Fixed object 19%/36% |
||||||
|
Longitudinal grooving |
21/37 |
54%/64% wet-road accidents,
ROR 40%/41%, rear-end/OT 35%/54%, Fixed object 19%/36% |
||||||
|
Transverse grooving |
--/-- |
Limited data |
||||||
|
|
|
|
||||||
|
Skid Treatment W/Overlay |
20/13 |
Open-graded mix most
effective. Right angle 23%/25%, Fixed
object 34%/26% |
||||||
|
Resurfacing with skid
resistant pavement |
13/8 |
42%/35% wet-road, right angle
23%/31% |
||||||
|
Resurfacing and superelevation |
28/28 |
Wet road 51%/51% |
||||||
|
Resurfacing w/open-graded mix |
75/75 |
Wet road 91%/91%, fixed
objects 93%/93%, head on/sideswipe 90%/90% |
||||||
|
Resurfacing w/Verglimit |
31/31 |
Icy road 52%/52% |
||||||
|
|
|
|
||||||
|
Side Slopes |
45/43 |
Fixed objects 62%/62% |
||||||
|
Flattening side slopes |
45/43 |
Fixed objects 62%/62% |
||||||
|
Flattening or clearing of side
slopes |
--/-- |
Limited data |
||||||
|
|
|
|
||||||
|
Improvement and/or Replacement of Structures |
|
|||||||
|
Widening existing bridge or
other major structure |
65/65 |
Collision w/bridge or other
major structure only |
||||||
|
Replacement of bridge or other
major structure |
25/25 |
|
||||||
|
Construction of new bridge or
major structure |
19/19 |
|
||||||
|
Construction or improvement of
minor structure |
--/-- |
Limited data |
||||||
|
Construction of pedestrian
over or under crossing |
--/-- |
Limited data |
||||||
|
Other structure work |
--/-- |
Limited data |
||||||
|
Alignment Work |
|
|
||||||
|
Horizontal alignment changes |
41/59 |
Fixed object 87%/68%, ROR
79%/90%, head-on 64%/67%, Rear end/OT 24%/73% |
||||||
|
Vertical alignment changes |
--/-- |
Limited data |
||||||
|
Horizontal & vertical alignment |
21/20 |
General reconstruction |
||||||
|
Roadside Appurtenances |
|
|
||||||
|
Traffic signs |
14/18 |
Rear end/OT 18%/21%, right turn 59%/--, right
angle --/34%, left turn --/35% |
||||||
|
Install/upgrade traffic signs |
13/28 |
Right angle 33%/43%, rear
end/OT 27%/33%, left turn 43%/51% |
||||||
|
Replace standard w/large stop
signs |
19/19 |
|
||||||
|
Install/improve warning signs |
--/-- |
Limited data |
||||||
|
Install/improve curve warning
signs |
--/-- |
Limited data |
||||||
|
Install/improve advance curve
warning flashers |
54/54 |
Night 62%/62% |
||||||
|
Install/improve other signs
(arrow signs) |
34/34 |
|
||||||
|
Protection/removal of fixed
object |
17/18 |
Rear end/OT 44%/42% |
||||||
|
Make breakaway signs or lights |
32/28 |
Rear end/OT 70%/72% |
||||||
|
Install clearance and/or
hazard markers |
--/-- |
Limited data |
||||||
|
Installation/Improvement of
Road Edge Guiderail |
13/16 |
Rear end/OT 28%/36%, Fixed
object 14%/16%, right angle --/17% |
||||||
|
Replace or upgrade deficient guiderail |
9/18 |
Guiderail 31%/40%, fixed-object
18%/23%, Rear end/OT 27%/41%, ROR 32%/42% |
||||||
|
Protection or removal of fixed
object in gore |
--/-- |
Limited data |
||||||
|
Install or upgrade culvert and
bridge railing |
20/22 |
Collision w/bridge or culvert
38%/37%, Rear end/OT 32%/34% |
||||||
|
Install road edge guiderail at new location |
10/10 |
Fixed object 4%/4%, increases
collision w/guiderail 51%/67%, ROR 18%/18%,
Rear end/OT 34%/31% |
||||||
|
Removal of guiderail (w/o other improves) |
(-19)/ (-19) |
Increase collisions
w/ditch/cut/bank 360%/411% |
||||||
|
Installation or Improvement of Median Barrier
(Physical Separation) |
20/56 |
Right angle 53%/30%, Rear
end/OT 32%/32%, Left turn 44%/44%, ROR 42%/42% |
||||||
|
Replace deficient median barrier |
--/-- |
Limited data |
||||||
|
Install median barrier |
19/19 |
Right angle 54%/58% |
||||||
|
Install or improve median
barrier near gore area |
17/17 |
ROR 56%/56%, increases
collision with guiderail 57%/57%, Rear end/OT
39%/39% |
||||||
|
Installation of Pavement
Markings and/or Delineators |
9/17 |
|
||||||
|
Install raised snow plowable pavement markings |
--/-- |
Limited data |
||||||
|
No-passing striping |
66/66 |
|
||||||
|
Centerline striping |
5/5 |
No passing striping 66%/66% |
||||||
|
Road edge restriping |
38/44 |
Fixed object 59%/66%, Rear
end/OT 50%/45% |
||||||
|
Delineation of shoulders |
9/9 |
|
||||||
|
Delineation of curves |
30/30 |
On curves of Radius <500ft |
||||||
|
Thermoplastic pavement
markings |
35/14 |
Fixed object 80%/56% |
||||||
|
Thermoplastic pavement
markings at spot locations |
22/22 |
Limited data |
||||||
|
OTHER ROADSIDE APPURTENANCES |
||||||||
|
Roadway lighting installation |
9/9 |
Spot locations 36%/36%, nighttime 67%/67% |
||||||
|
Improve drainage &/or
drainage structures |
32/32 |
|
||||||
|
Fencing installation |
--/-- |
Limited data |
||||||
|
Install impact attenuators |
4/4 |
Limited data |
||||||
|
Shoulder rumble strips |
--/-- |
Limited data |
||||||
|
|
|
|
||||||
|
Improvements at gores |
31/23 |
Right angle 60%/51%, Rear
end/OT 44%/50%, Head on/SS 43%/34%, ROR 52%/56% |
||||||
|
Protection from fixed
objects/improvement of positive guidance in gore area |
35/27 |
Rear-end/sideswipe 45%/53%,
run-off-the road 46%/46%, fixed object 18%/18% |
||||||
|
Thermoplastic striping &
delineation in gore area |
94/38 |
Rear-end/sideswipe 64%/51% |
||||||
|
Removal or protection of fixed
objects in gore area |
7/7 |
Rear-end/sideswipe 32%/42%, ROR 74%/84% |
||||||
Source: NYSDOT Traffic Engineering and Safety
Division Safety Program Management Bureau, 5/00
Table H-1A
Supplemental accident Reduction Factors
|
Improvement |
Average
Reduction |
Remarks/Source |
|
|||||||||||
|
Consolidation of driveways |
20/20 |
NYSDOT's 1995/1996 Five-Year
Program included an estimate of a 26%
reduction in accidents at locations where arterial management techniques are
applied including consolidating driveways, inter-connecting parking lots,
installation of frontage roads, etc. Azzeh et.
al reported an estimated 20% reduction
in accidents after consolidation of
driveways. |
|
|||||||||||
|
Installation of service roads |
17/17 |
Wolf Road/Exit 3 Area
Transportation System Study Planning Report, CDTC, March 1990 |
|
|||||||||||
|
Installation of sidewalks |
50/50 |
FHWA's
Investigation of Exposure-based Pedestrian Accident Areas: Crosswalks,
Sidewalks, Local Streets and Major Arterials. RD -88-038, Applied against pedestrian/mv accidents only |
|
|||||||||||
|
Painted and/or raised bicycle
crossing at intersections - assumed to be installed with all bike lane
projects |
30/30 |
An estimated reduction of 30%
in bicycle/motor vehicle accidents due to installation of raised and painted
bike lane/path intersection crossing (Garder, Leden, and Pulkkinen, 1998) Applied against bicycle/mv
accidents only |
|
|||||||||||
|
Traffic calming (bulb outs,
etc) |
40/40 |
Estimated 40% reduction in all
intersection accidents from traffic calming aggregating for all improvement
types including bulbouts, narrowings,
crosswalks, etc. according to "Safety Benefits of Traffic Calming",
Zein, Geddes, Hemsing, Johnson, 1997, Transportation Research Record
1578. Applied against intersection accidents only |
|
|||||||||||
|
Installation of pedestrian
refuge island |
57/57 |
Geddes et al found the following
levels of accident reduction: traffic circles and chicanes, 82 % … multiple
measures 65% … pedestrian refuges 57%.
"Safety Benefits of Traffic Calming", Zein,
Geddes, Hemsing, Johnson,
1997, Transportation Research Record 1578. |
|
|
|
|
|
|
|
|
|
|
||
|
Installation of Roundabout |
39/39 |
According to Insurance Institute for Highway Safety
as published in "Crash Reductions Following Installation of Roundabouts
in the |
|
|
|
|
|
|
|
|
|
|
||
Average Accident Costs
|
Facility Type |
Average |