PLANNING
COMMITTEE MEETING
Meeting Minutes
November 4, 2009
Melissa Ashline-Heil, City of Cohoes
Bradley Birge, City of Saratoga Springs
Wayne Bonesteel, representing Fred Howard, Rensselaer
County
Peter Comenzo, Town of Rotterdam
Michael Franchini, Albany County (Chairman)
Robert Hansen, NYS Department of Transportation Region 1
Steve Iachetta, Albany County Airport Authority
Barb McHugh, Town of Clifton Park
Mike Morelli, Town of Bethlehem
Marybeth Pettit, City of Rensselaer
Paul Reuss, Village of Menands
Joe Rich, Federal Highway Administration
Tom Richardson, City of Mechanicville
Jim Rivers, representing Bill Roehr, City of Troy
Deidre Rudolph, City of Albany
Michael Valentine, Saratoga
County
Steve Watts, Town of Halfmoon
STAFF
Don Adams, Creighton Manning
Jeff Buel, City of Troy
Jen Ceponis, Capital District Transportation Committee
Joe Cimino, Clough Harbour Associates
David P. Jukins, Capital District Transportation
Committee
Sandra Misiewicz, Capital
District Transportation Committee
Sree Nampoothiri, Capital
District Transportation Committee
Tom Owens, Albany Port
District Commission
Susan Pedo, The Walters Group
Angelo Trichilo, NYS
Department of Transportation, Region 1
Mike Wyatt, NYS Department of
Transportation, Region 1
VISITORS ISSUES
Action Items
SPECIAL PRESENTATION
NYSDOT Report on the Design
of I-87 Exit 3/4 (TIP A240)
Angelo Trichilo from NYSDOT provided information about
the I-87 Exit 3/4 project. The objective
of the project is to improve access to the Albany Airport without impacting the
already congested mainline. The project is meant to improve the connection
between Wolf Road and the airport, replace the Albany Shaker Road Bridge over
the Northway and to improve bicycle/pedestrian amenities along Wolf Road and to
and from the Airport. Four alternatives
are being scrutinized:
1.
Upgrade Exit 4 ($23M +
$2.0-17.0M
2.
Replace the bridges at Wolf
Road and Albany Shaker Road and construct a modified diamond interchange with a
connection to Marcus Blvd ($44.0M + $7.5M
3.
Construct a partial
interchange south of Exit 4 and replace the bridges over Albany Shaker Road ($34.5M
+ $17.5M
4.
Replace Exit 4 with a single
point interchange, cul-de-sac Old Wolf Road and re-align the northern end of
Wolf Road ($50.0M + $2.7-9.7M
NYSDOT will showcase these options to the public in the spring
(2010); FHWA approval is required to add an interchange. NYSDOT must demonstrate that an additional
interchange will not degrade the function of the mainline. NEPA and SEQRA are also required. Once an alternative is agreed upon,
construction will begin in 2013.
Steve Iachetta reminded members that the Albany airport
is one of the few in the nation that does not have direct access from an
interstate and that this lack of direct access could have negative economic
impacts to the region.
ADMINISTRATION
Approval
of the October 7, 2009 Meeting Minutes
Members approved the October 7th meeting
minutes as written.
MPO Planning Agreement
The Planning Agreement in the previously distributed
material is an elaboration of the agreement that was distributed to members at
the August 5th Planning Committee meeting, as per a FTA/FHWA. Two typos were identified—the word “it’s” in
the first paragraph of the MOU should be “its” and the word “active” in the
first paragraph on page 4 should be “actively”.
Members approved the agreement as corrected. The agreement will be distributed to CDTC’s
Policy Board and CDTA’s Board for approval.
NYSDOT Commissioner Stan Gee will be asked to sign the agreement.
Air
Quality Conformity MOU
Chris O’Neill described the agreement between CDTC and
A/GFTC regarding conformity activities. Members approved the MOU between CDTC and
A/GFTC and recommended the MOU for Policy Board approval. Chris also described the results of the most
recent Conformity Analysis that was necessitated because A/GFTC is updating
their Long range Plan. Members approved releasing
the conformity analysis for public review.
Prospectus
Update
AMERICAN RECOVERY
CDTC/NYSDOT
Report on Project Implementation
2010-15 TRANSPORTATION
IMPROVEMENT PROGRAM UPDATE
Screening,
Merit Evaluation and Possible Process Changes—An annotated version of the handout entitled, “
Programming
Targets—The document entitled, “Use of New
Visions Budgets for Round One Programming Targets” was discussed. Members agreed with the strategies outlined
in the document. Members noted that “not
eligible for funding” in the comment column under # 9 in Table 1 should be removed.
Summary of
the 2008 and 2009 New Freedom Projects—
¨ Catholic Charities of
Schenectady County and the Schenectady County ARC will purchase, install, and
maintain trip scheduling and dispatch software and coordinate trips between the
two agencies. Status—almost complete.
¨ Catholic Charities of
Schenectady County requested funds to conduct a feasibility study of expanding
weekend service to seniors, most of whom are frail and mobility challenged. Catholic
Charities has done a lot of work on this project. Status--Demand responsive accessible
transportation service on weekends began on October 31, 2009.
¨ The city of Watervliet
requested funds to purchase a 12-15 passenger accessible vehicle that would be
used to start feeder transit service within the city, connecting senior housing
to retail and recreational facilities.
The feeder service will connect to CDTA’s fixed route serve and will
serve a limited section of Green Island. Status—the first advisory committee
meeting was held on October 29, 2009.
At the end of the second solicitation, approximately
$342,600 in federal New Freedom funds remained un-programmed. The RTCC asked CDTA to submit an application
for the remaining funds to introduce an accessible taxi program in the Capital
Region; CDTA agreed.
CDTA is currently working out the particulars for an
accessible taxi program. As long as the
legal details (such as medallions, driver training and drug testing) can be
addressed, the remaining New Freedom allocation will be programmed.
Changes to
Project Selection Procedures-Material on this item was in
member’s packets. This material was not
discussed in depth at the meeting, due to time constraints. The items listed in this material will have
to be resolved before staff begins to evaluate the proposed TIP projects.
2009-14 TRANSPORTATION
IMPROVEMENT PROGRAM AMENDMENTS
TIP Project
R195—South Troy Industrial Park Road
TIP project R195 has been listed in the TIP for quite
some time. Approximately $900,000 in PE
remains for the project. The city would
like a scope change to extend the southern boundary of the original project and
examine a southern connection to the Troy/Menands Bridge. The city recently acquired land near the
bridge and believes that the industrial road should connect to Route 378 on the
southern end. The city also initially proposed
that the $5.298M in construction be used for the southern end of the Road, and
requested an additional $3.8M for construction of the northern section of the
road. Early in the discussions about
this project, the city withdrew the request for the additional $3.8M for
construction.
TIP
Project SA221—Geyser Road Bridge over D & H Railroad
This amendment asks for an additional $584,000 for the
construction phase of the project. There is a minor cost increase to this
project for the PE Phase. Approximately
$40,000 in additional funds is required for the PE Phase. This project will be
funded using ARRA funds. Members
approved the amendment, noting that the increase in PE must be shown.
Discussion Items
UNIFIED PLANNING
2010-12
UPWP Development—Schedule, Budget and Emphasis Areas
In the interest of time, this agenda item was skipped.
Report on
Bicycle Education Project
In the interest of time, this agenda item was skipped.
STATUS OF PLANNING
In the interest of time, this agenda item was skipped.
OTHER
There being no other business, the meeting was adjourned
at 1:05 p.m. The next Planning Committee
meeting is scheduled for January 6th 2010.
Respectfully submitted,